What should be recorded in a construction handover minute

This guide explains, from the angle of the working file, what ought to appear in a minute drawn up when construction work in the city is handed over: a build, a repair, or the completion of a structure. It is not a guide to the contractor's duties under numbered articles, and it is not a general defects list. The aim is that both parties can later tell what was handed over, when, and under what reservation.

The minute is usually kept with the contract and the approved drawings. If the work on site differs from the drawing, the difference is stated in the minute, rather than relying on a general signature of "receipt".

Entries in the minute that later prevent a dispute about what was handed over

The date of the inspection, the location of the property, and the names of those present for the employer and for the contractor are stated, together with the stage: a partial handover of part of the work, or a final handover. The works handed over are identified by reference to a contract item or to a drawing sheet, not by a loose phrase. If measurements or dated photographs exist, they are referred to as numbered annexes.

The minute should also record any keys, "as-built" drawings, or equipment warranties that form part of the obligation. The absence of that note does not erase the obligation if the contract proves it, but it weakens proof if the parties later disagree.

Reservations and postponed items after a partial handover

If items remain incomplete, or a defect appears at the inspection, the reservation is written clearly: what it is, where it is on site, and whether a time was agreed for putting it right. A handover with a reservation is not the same as an unqualified handover. Signing without reading what was written in blank fields later opens a dispute about what was "taken to have been delivered".

This guide is for awareness in preparing the paper. The detail of a dispute after handover is on the page about construction contracts and building disputes.